PHE Renewal Project
@ Leading EU Steel Plant
Jul23, 2024
We have recently delivered a turnkey plate pack renewal project for two (2) Plate Heat Exchanger units onsite a leading EU steel production plant.
Maritech studied the specifications of the old/existing equipment and consequently fabricated, installed and tested new plate packs with perfect fit and optimized thermal efficiency.
Work Scope:
• Dismantling of units
• Inspection and frame set restoration
• Fabrication of new plates
• Installation of plate packs
• Pressure Testing
The Challenge
Our Plate Heat Exchanger specialists fulfilled the plant’s safety requirements and successfully met the 48-hour predetermined timeframe by working in shifts around-the-clock.
Outcome
All works were completed successfully and results cross-checked by plant’s Quality Manager.